Excel-like filter in Vue Gantt Chart Component

18 Nov 201810 minutes to read

You can enable the Excel-like filter by setting the https://ej2.syncfusion.com/vue/documentation/api/gantt#filtersettings property to Excel. The Excel filter menu includes options such as Sorting, Clear Filter, and an Advanced Filtering submenu.

<template>
     <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :columns="columns" :splitterSettings = "splitterSettings" :filterSettings="filterSettings" :allowFiltering= "true"></ejs-gantt>
    </div>
</template>
<script setup>
import { provide, ref } from "vue";
import { GanttComponent as EjsGantt, Filter, } from "@syncfusion/ej2-vue-gantt";
import { projectNewData } from './data-source.js';
const data = [
    {
        TaskID: 1,
        TaskName: 'Project initiation',
        StartDate: new Date('04/02/2019'),
        EndDate: new Date('04/21/2019'),
        subtasks: [
            {TaskID: 2, TaskName: 'Identify site location', StartDate: new Date('04/02/2019'), Duration: 0,Progress: 50, resources: [1]},
            {TaskID: 3, TaskName: 'Perform soil test', StartDate: new Date('04/02/2019'), Duration: 4, Predecessor: '2',Progress: 50, resources: [2, 3, 5]},
            {TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 0, Predecessor: '3', Progress: 50 },
        ]
    },
    {
        TaskID: 5,
        TaskName: 'Project estimation',
        StartDate: new Date('04/02/2019'),
        EndDate: new Date('04/21/2019'),
        subtasks: [
            {TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'),Duration: 3, Predecessor: '4', Progress: 50, resources: [4]},
            {TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'),Duration: 3, Predecessor: '6', resources: [4, 8],Progress: 50},
            {TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'),Duration: 0, Predecessor: '7', resources: [12, 5]}
        ]
    }];
const height = '450px';
const columns = [
    { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
    { field: 'TaskName', headerText: 'Task Name', width: '250' },
    { field: 'StartDate', headerText: 'Start Date', width: '150' },
    { field: 'Duration', headerText: 'Duration', width: '150' },
    { field: 'Progress', headerText: 'Progress', width: '150' },
];
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    duration: 'Duration',
    progress: 'Progress',
    child: 'subtasks'
};
const splitterSettings = {
    columnIndex:3
};
const filterSettings = {
    type:'Excel'
};
provide('gantt',  [ Filter]);
</script>
<template>
     <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :columns="columns" :splitterSettings = "splitterSettings" :filterSettings="filterSettings" :allowFiltering= "true"></ejs-gantt>
    </div>
</template>
<script>

import { GanttComponent, Filter, } from "@syncfusion/ej2-vue-gantt";
import { projectNewData } from './data-source.js';

export default {
name: "App",
components: {
"ejs-gantt":GanttComponent
},
  data: function() {
      return{
            data: [
    {
        TaskID: 1,
        TaskName: 'Project initiation',
        StartDate: new Date('04/02/2019'),
        EndDate: new Date('04/21/2019'),
        subtasks: [
            {TaskID: 2, TaskName: 'Identify site location', StartDate: new Date('04/02/2019'), Duration: 0,Progress: 50, resources: [1]},
            {TaskID: 3, TaskName: 'Perform soil test', StartDate: new Date('04/02/2019'), Duration: 4, Predecessor: '2',Progress: 50, resources: [2, 3, 5]},
            {TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 0, Predecessor: '3', Progress: 50 },
        ]
    },
    {
        TaskID: 5,
        TaskName: 'Project estimation',
        StartDate: new Date('04/02/2019'),
        EndDate: new Date('04/21/2019'),
        subtasks: [
            {TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'),Duration: 3, Predecessor: '4', Progress: 50, resources: [4]},
            {TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'),Duration: 3, Predecessor: '6', resources: [4, 8],Progress: 50},
            {TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'),Duration: 0, Predecessor: '7', resources: [12, 5]}
        ]
    }],
            height: '450px',
            columns: [
            { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
            { field: 'TaskName', headerText: 'Task Name', width: '250' },
            { field: 'StartDate', headerText: 'Start Date', width: '150' },
            { field: 'Duration', headerText: 'Duration', width: '150' },
            { field: 'Progress', headerText: 'Progress', width: '150' },
        ],
        taskFields: {
            id: 'TaskID',
            name: 'TaskName',
            startDate: 'StartDate',
            duration: 'Duration',
            progress: 'Progress',
            child: 'subtasks'
        },
        splitterSettings:{
            columnIndex:3
            },
        filterSettings: {
            type:'Excel'
        },
        };
  },
  provide: {
      gantt: [ Filter]
  }
};
</script>