Enum TaskConstraintType
Defines the constraint types applied to tasks in Gantt scheduling.
Namespace: Syncfusion.Blazor.Gantt
Assembly: Syncfusion.Blazor.Gantt.dll
Syntax
public enum TaskConstraintType
Fields
| Name | Description |
|---|---|
| AsLateAsPossible | The task starts as late as possible without delaying the project. |
| AsSoonAsPossible | The task can start as early as possible based on its dependencies. |
| FinishNoEarlierThan | The task cannot finish earlier than the specified constraint date. |
| FinishNoLaterThan | The task cannot finish later than the specified constraint date. |
| MustFinishOn | The task must finish on a specified date. |
| MustStartOn | The task must start on a specified date. |
| StartNoEarlierThan | The task cannot start earlier than the specified constraint date. |
| StartNoLaterThan | The task cannot start later than the specified constraint date. |