Getting Started with Vue Gantt Chart in Vue 3
This article provides a step-by-step guide for setting up a Vite project with a JavaScript environment and integrating the Vue Gantt Chart component using the Composition API.
Prerequisites
- Node.js 24+ (LTS recommended).
- Syncfusion CLI.
Install the Syncfusion CLI
Install the Syncfusion CLI globally using the following command:
npm install -g @syncfusion/syncfusion-cliSet up the Vite project using Syncfusion CLI
You can create a Vue application with Vite using the Syncfusion CLI. The CLI provides two ways to create a project:
Non-interactive mode
Non-interactive mode allows you to create a project directly using a single command with the required command-line arguments.
sf new my-project --framework vue --template ganttIn this mode, the project configuration is passed directly in the command. The above command creates a Vue application with Vite and configured it with the Syncfusion® Gantt component. The generated project uses the TypeScript and the Composition API.
Interactive mode
Interactive mode guides you through the project creation process with step-by-step prompts.
sfWhen you run the sf command, the CLI prompts you to select the required project configuration options. To create a Vue application with Vite and the Syncfusion® Gantt component, select the following options:
√ Project name? ... my-project
√ Choose Framework: » Vue
√ Choose Language: » JavaScript
√ Choose Template: » Gantt
√ Choose Theme: » Material3
√ Choose Style Format: » CSS
√ Would you like to integrate the Syncfusion MCP Server (AI Assistant) into this project? ... no
√ Would you like to install Syncfusion Component Skills for AI-powered development? ... no
√ Install dependencies and start app now? ... noThe above selections generate a Vue application with Vite and configure it with the Syncfusion® Gantt component. You can choose different values for language, theme, style format, MCP setup, and skills installation based on your project requirements.
The Syncfusion® CLI creates the project with a predefined template. After the project is generated, you can customize or replace the component code based on your application requirements.
Run the project
Once the project is created, navigate to the project directory and run the following commands in your terminal.
cd my-project
npm install
npm run devThe output will appear as follows:

Prerequisites
Before you begin, make sure that:
- Node.js and npm (or Yarn) are installed.
- Vite and Vue 3 are supported in your environment.
- You are using a supported version of the Syncfusion Vue package for your project.
For compatibility details, see System requirements for Syncfusion® Vue UI components.
Set up the Vite project
A recommended approach for beginning with Vue is to scaffold a project using Vite. To create a new Vite project, use one of the commands that are specific to either NPM or Yarn.
npm create vite@latest
or
yarn create vite
Using one of the above commands will lead you to set up additional configurations for the project as below:
1.Define the project name: The name of the project can be specified directly. For this article, the project name is set as my-project.
? Project name: » my-project
2.Select Vue as the framework. It will create a Vue 3 project.
? Select a framework: » - Use arrow-keys. Return to submit.
Vanilla
> Vue
React
Preact
Lit
Svelte
Others
3.Choose JavaScript as the framework variant to build this Vite project using JavaScript and Vue.
? Select a variant: » - Use arrow-keys. Return to submit.
> JavaScript
TypeScript
Customize with create-vue ↗
Nuxt ↗
4.Install dependencies and start the development server.
Install with npm and start now?: Yes
Since you selected Yes, the development server should start automatically. If you selected No, please follow these steps to set up and start the project manually:
cd my-project
npm install
or
cd my-project
yarn install
Now that my-project is ready to run with default settings, let’s add Syncfusion® components to the project.
Add Syncfusion® Vue packages
Syncfusion® Vue component packages are available at npm package registry. To use Syncfusion® Vue components in the project, install the corresponding npm package.
This article uses the Vue Gantt Chart component as an example. To use the Vue Gantt Chart component in the project, install the @syncfusion/ej2-vue-gantt package using the following command:
npm install @syncfusion/ej2-vue-gantt
or
yarn add @syncfusion/ej2-vue-gantt
Adding CSS reference
Themes for Syncfusion® Gantt Chart components can be applied using CSS files provided through npm theme packages. For available themes, refer to the Themes documentation.
Install the Tailwind 3 theme package using the following command:
npm install @syncfusion/ej2-tailwind3-theme --saveThen add the following CSS reference to the src/App.vue file:
<style>
@import "../node_modules/@syncfusion/ej2-tailwind3-theme/styles/gantt/index.css";
</style>Create sample data
Define a simple task list with hierarchical relationships. Each task must have a StartDate and either a Duration or EndDate to render properly.
const data = [
{
TaskID: 1,
TaskName: "Project initiation",
StartDate: new Date("2024-04-01"),
EndDate: new Date("2024-04-15"),
},
{
TaskID: 2,
TaskName: "Identify site location",
StartDate: new Date("2024-04-01"),
Duration: 4,
Progress: 70,
ParentID: 1,
},
{
TaskID: 3,
TaskName: "Perform site survey",
StartDate: new Date("2024-04-01"),
Duration: 4,
Progress: 50,
ParentID: 1,
},
{
TaskID: 4,
TaskName: "Soil testing",
StartDate: new Date("2024-04-01"),
Duration: 3,
Progress: 40,
ParentID: 1,
},
{
TaskID: 5,
TaskName: "Project estimation",
StartDate: new Date("2024-04-08"),
EndDate: new Date("2024-04-18"),
},
{
TaskID: 6,
TaskName: "Develop floor plan",
StartDate: new Date("2024-04-08"),
Duration: 5,
Progress: 30,
ParentID: 5,
},
{
TaskID: 7,
TaskName: "Estimate project cost",
StartDate: new Date("2024-04-08"),
Duration: 5,
Progress: 20,
ParentID: 5,
},
];
Configure task fields
const taskFields = {
id: "TaskID",
name: "TaskName",
startDate: "StartDate",
duration: "Duration",
progress: "Progress",
parentID: "ParentID",
};
Field mapping reference
| Property | Description | Required |
|---|---|---|
id |
Unique task identifier | Yes |
name |
Task display name | Yes |
startDate |
Task start date | Yes |
duration |
Task duration in days | Yes |
progress |
Task completion percentage (0-100) | No |
parentID |
Parent task ID for hierarchy | No |
Render the Gantt Chart component
Replace the default src/App.vue content with the following example, or add the sample code to your existing App.vue file. Import and register the Gantt Chart component in the <script> section, and use the setup attribute in the <script> tag to enable the Composition API.
To display the Gantt Chart, bind your task data using the dataSource property and map the corresponding fields using the taskFields property.
<template>
<ejs-gantt
:dataSource="data"
:taskFields="taskFields"
>
</ejs-gantt>
</template>
<script setup>
// Import and register the Gantt Chart component
import { GanttComponent as EjsGantt} from '@syncfusion/ej2-vue-gantt';
const data = [
{TaskID: 1, TaskName: 'Project initiation', StartDate: new Date('2024-04-01'), EndDate: new Date('2024-04-15')},
{TaskID: 2, TaskName: 'Identify site location', StartDate: new Date('2024-04-01'), Duration: 4, Progress: 70, ParentID: 1},
{TaskID: 3, TaskName: 'Perform site survey', StartDate: new Date('2024-04-01'), Duration: 4, Progress: 50, ParentID: 1},
{TaskID: 4, TaskName: 'Soil testing', StartDate: new Date('2024-04-01'), Duration: 3, Progress: 40, ParentID: 1},
{TaskID: 5, TaskName: 'Project estimation', StartDate: new Date('2024-04-08'), EndDate: new Date('2024-04-18')},
{TaskID: 6, TaskName: 'Develop floor plan', StartDate: new Date('2024-04-08'), Duration: 5, Progress: 30, ParentID: 5},
{TaskID: 7, TaskName: 'Estimate project cost', StartDate: new Date('2024-04-08'), Duration: 5, Progress: 20, ParentID: 5}
];
const taskFields = {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
duration: 'Duration',
progress: 'Progress',
parentID: 'ParentID'
};
</script>
<style>
@import "../node_modules/@syncfusion/ej2-tailwind3-theme/styles/gantt/index.css";
</style>Run the application
Run the application using the following command:
npm run dev
The development server usually starts on http://localhost:5173. If it does not start, verify that the dependencies were installed successfully and that you are running the command from the project folder.
Output
You will see a Gantt Chart with:
- Task hierarchy with parent-child relationships
- Timeline view showing task bars
- Progress indicators on each task
- Automatically calculated dates based on duration
The chart displays two parent tasks (“Project initiation” and “Project estimation”) with their subtasks shown in a tree structure. Task bars are rendered on the timeline, sized according to their duration and start dates.

Web server will be initiated, Open the quick start app in the browser at port localhost:8080.
Next Steps
- Key Elements - Learn about UI components and interactions
- Feature Modules - Enable advanced features with module injection
- Overview - Explore all available features