Change workweek/working days in a week
Non-working days/weekend are used to represent the non-productive days in a project. It is possible to change the non-working days in a week using the WorkWeek
property in Gantt.
By default, Saturdays and Sundays are considered as non-working days/weekend in a project.
The following code example explains how to change weekend/non-working days
@(Html.EJ().Gantt("gantt")
.WorkWeek(new List<string>() { "Sunday","Monday","Tuesday","Wednesday","Thursday" })
)
@(Html.EJ().ScriptManager())
The above screen shot will be displayed after changing the non-working days in Gantt.